CEQA FINDINGS

 

The California Environmental Quality Act and County Environmental Review Guidelines require that when an EIR has been completed which for a project identifies one or more significant environmental effects for the project, the public agency shall not approve the project unless one or more of the following findings can be made:

 

1.         Changes or alterations have been required in, or incorporated into the project which avoid or substantially lessen the significant environmental effect as identified to the final EIR.

 

2.         Such changes or alternations are with the responsibility and jurisdiction of another public agency and not the agency making the finding.  Such changes have been adopted by such agency or can and should be adopted.

 

3.         Specific economic, social or other considerations make infeasible the mitigation measures or project alternatives, identified in the final EIR.

 

The final Environmental Impact Report for the Pajaro River and Salsipuedes and Corralitos Creeks EIR (EIR) includes the Draft and Final EIR dated August 31, 2001 and February 2002 respectively.  The EIR has identified, as significant, the impacts described below.  Changes have been incorporated into the project or mitigations have been specified for permit conditions which can reduce all identified impacts to levels of insignificance.  Project mitigations are described directly below each impact listed on the following pages of these findings.  All mitigation measures listed on the following pages have been incorporated into the project design or they have been made a condition of the project. CEQA finding #1 pertains to all impacts on the following pages. 

Impacts which are less than significant are listed following the significant impacts and  corresponding mitigation measures.

 

 

HYDROLOGY AND WATER QUALITY

Impact H-2.  Construction of bank protection measures may reduce hydraulic capacity within the levees and increase the threat of flooding.

Installation of bank protection would reduce the cross-sectional area available for flood flows, potentially resulting in higher flood levels and increased risk of flooding adjacent areas.  In addition, bank protection measures could trap sediment, causing the bank to increase in width over time and reduce hydraulic capacity.  This is a significant impact.

Mitigation Measure H-2.  To prevent reduction of hydraulic capacity of project streams, bank protection measures shall not be constructed unless studies show that; 1) hydraulic capacity would not be decreased below current (year 2001) capacity; and 2) erosion is substantial enough to threaten the adjacent levee.  These studies should include the following:

·        A topographic survey of the Pajaro River and Salsipuedes Creek channels to establish baseline             (year 2001) bank topography information;
·        Field observation of the affected bank vicinity to determine if previous bank armoring exists;
·        Annual monitoring after significant storm events to determine the presence and rate of bank              erosion;
·        Field measurements from new (damaged) toe of bank to toe of levee to compare to baseline              (year 2001) conditions; and
·        Engineering analysis of channel capacity with proposed armoring in place (HEC-2 or HEC-RAS              computer models).

The river shall be monitored annually and after significant storm events to identify the presence of bank erosion.  Erosive areas shall be evaluated for their potential to erode further and pose a threat to the levee.  The degree of threat depends upon the geometry in the erosion areas.  Factors to be considered should include the distance of bank retreat, local geometry that suggests an increased threat (such as the presence of bends, contractions, or abutments), and the presence (or lack of) existing bank protection.

Impact H-3.  Temporary construction activities would generate sediment in the area of bank protection construction.

Construction activities associated with stream bank armoring would disturb surrounding areas and result in denuded areas that are temporarily susceptible to erosion.  Additionally, the proposed bank protection features include excavation and compaction of earth materials.  Until vegetation becomes established, these areas would be prone to erosion resulting in a significant impact.  Implementation of the mitigation described below would reduce this impact to less than significant levels.

Mitigation Measure H-3.  To reduce the potential for erosion and sedimentation in the adjacent river, the final design of proposed bank protection shall include preparation of an erosion control plan that incorporates requirements of the County of Santa Cruz Grading Ordinance, Erosion Control Ordinance, County Design Criteria and the Construction Activities General Permit.  The plan shall be reviewed and approved by County Planning and applicable regional and State agencies, when required, prior to the commencement of any construction activity.  All provisions of the approved plan shall be followed during construction.

Compliance with these requirements would necessitate preparation of an erosion control plan to minimize erosion during and following construction of bank protection.  Standard best management practices shall be included in the plan, such as placement of silt fences, straw-bale dikes, or check dams and revegetation of barren slopes immediately following construction.  The type of measures will vary depending upon location and type of armoring proposed.

Impact H-4.  Use of the herbicides Roundup and Rodeo to control vegetation growth along levee benches and slopes could adversely impact water quality.

Roundup and Rodeo are extensively used herbicides manufactured by Monsanto Company.  Glyphosate, the active ingredient of Roundup and Rodeo, is a wide-spectrum, non-selective herbicide that is effective against perennial grasses, broad-leaved weeds and shrubs.  Glyphosate is absorbed almost exclusively by plant foliage and is then translocated throughout the plant by the plant’s circulatory system.  Once in the soil, glyphosate is broken down into natural materials by soil microflora and has little potential to move in the ground to affect nearby, untreated plants.  Therefore, glyphosate-based herbicides are often selected because of their effectiveness in killing only the plants that are directly sprayed.  Rodeo and Roundup are similar except that (1) Rodeo contains a more concentrated form of glyphosate and (2) Roundup contains polyethoxylated tallowamine (POEA), a surfactant (an agent that attaches itself to suspended material) that can have toxic effects in water systems.  Because Rodeo contains no POEA, the Environmental Protection Agency’s Office of Pesticide Programs has approved its use over open water and wetlands.

Mitigation Measure H-4.  To sustain non-toxic effects to aquatic wildlife, Rodeo and Roundup herbicides shall be applied in such a manner as to avoid over-spray or application of Roundup in or adjacent to surface water.

Application methods proposed by the applicant would minimize the potential for adverse impacts from herbicide use to less than significant levels.  These methods include: 

·        Use of herbicide at or below concentrations recommended by the manufacturer.

·        Use of proper precautions to avoid spills.

·        Worker training to ensure that herbicide is sprayed only on target vegetation.

·        Use of Roundup herbicide for on-land application only.

·        Minimal in-channel use of Rodeo herbicide.

 

It is not anticipated that large quantities of vegetation would be sprayed in the river or creek channels.  Application of herbicide in the channel would be limited primarily to “painting” the stems of woody vegetation greater than 3 inches in diameter.  If large scale spraying of vegetation in the channel is required, however, the County would remove the dead vegetation entirely from the channel.

GEOLOGY AND SOILS

 

Impacts from Levee Resurfacing

 

Impact G-2.  Levee maintenance may cause accelerated erosion along levee slopes.

The proposed levee maintenance activities include minor grading to repair levee roads and application of herbicides on levee tops and some slopes areas and on benches to control growth of vegetation.  Grading will result in bare, un-vegetated soil that can become susceptible to accelerated erosion from wind, rain or scour from flooding.  Similarly, the application of herbicide would kill vegetation whose root systems would otherwise stabilize levee slopes.  This would also cause accelerated erosion from rain and scour from flooding.  Therefore, levee maintenance may significantly accelerate erosion on levee slopes.

Mitigation Measure G-2.  To prevent accelerated erosion of repaired levee slopes, graded areas shall be revegetated prior to October 15 of the same year that repair work occurred.

To prevent rainfall or stream flow induced erosion of recently repaired or maintained levee slopes, Public Works maintenance crews should apply grass seed and mulch material to bare soils immediately after grading and related maintenance activities have been completed.  On bare levee slopes exceeding 15%, the mulch shall be secured with jute netting stapled into the soil according to accepted erosion control practices.  In all cases all erosion control measures shall be completed prior to October 15 of the year the maintenance/repair work was done.  Additionally, the mitigation measures as described in H-3 shall be implemented.

Impacts from Bank Erosion Repair

 

Mitigation Measure G-3b: Construction period effects.  See Impact H-3 and G-2.  Mitigation Measure H-3 and G-2 will be implemented on a site-specific basis and will consider time of year to implement measures, soil containment during construction, slope stabilization after construction and access for heavy equipment used for repairs.

Repairs shall be done in late summer (June 1 to October 15) to minimize impacts to steelhead and other aquatic wildlife from sedimentation.  An erosion control plan shall be prepared to minimize erosion during and following construction of bank protection as in Mitigation Measure H-3.  Standard best management practices shall be included in the plan, such as placement of silt fences, straw-bale dikes, or check dams and revegetation of barren slopes immediately following construction.  The type of measures will vary depending upon location and type of armoring proposed.  Mitigation Measure G-2 will be implemented to stabilize slopes after construction and BMPs shall consider access routes of heavy equipment to minimize further erosion and disturbance to vegetation. 

Impact G-4.  Implementation of bank erosion repairs on the Santa Cruz County side of the Pajaro River could cause increased erosion and bank movement on the Monterey County side.

Under the proposed project, bank erosion repairs and revegetation of channel banks will be performed exclusively on the Santa Cruz County side of the Pajaro River.  Installation of new bank protection could change flow characteristics in the area of bank repair, including flow direction, velocity and sediment carrying capacity.  Erosion potential on the Monterey side of the Pajaro River may change as a result of changes in channel depth, velocity, or angle-of-attack.  This could cause an increase in erosion from scour and subsequent bank movement on the Monterey County side.  This would be a significant impact.

Mitigation Measure G-4.  To prevent increased erosion and bank movement of the Monterey County side of the Pajaro River, mitigation H-2 should be implemented as part of any stream bank repair on the Santa Cruz County side of the river. 

The mitigation measures described in H-2 would eliminate potential adverse impacts to the Monterrey County side in relation to the baseline 1999-2000 conditions.  This work shall include review of the results of the HEC model (see Mitigation Measure H-2) for velocity and depth changes in relation to the year 2000 condition.  Additionally, the engineering analysis shall consider the potential for proposed improvements to act as a “vane” to direct flows toward the Monterey County banks.  If revegetation is proposed as part of the bank improvements or if sediment would be expected to deposit along the bank as a result of the improvement, the hydraulic analysis should consider these factors.

Impacts from Revegetation and Channel Maintenance

Impact G-5.  Proposed tree planting along the inner channel benches of the Pajaro River could threaten levee and/or bank stability.

The proposed revegetation activities include planting trees sporadically along benches.  If the bench is too narrow or the tree is planted too close to the edge of the bench, the tree may be unable to stabilize and could fall over, taking portions of the bank with it as it falls.  Tree failure could increase bank erosion potential during flooding, resulting in levee instability or infilling of the river channel.  However, under the proposed project no trees will be planted where the inner channel bench is less than 10’ feet wide and will restrict tree planting to channel benches that are at least 32’ wide.  As a result of these design measures, the potential for this impact would be considered less than significant.

Mitigation Measure G-5.  To ensure channel and bank stability, design features identified in Impact G-6 shall be implemented.

To ensure that bank and or/levee stability is not threatened from tree planting along the inner benches of the Pajaro River, trees shall not be planted closer than 8 feet to the edge of the channel bank.

Impact G-8.  Installed bank protection measures could fail due to flanking flows if not properly installed.

Failure of bank protection measures could occur from erosion behind the bank surface, due to either inadequate placement of a filter blanket under the protection measures or flows over the bench areas cutting substantially behind the bank. 

Mitigation Measure G-8.  To protect failures of new bank protection measures, the design of rock armoring or toe protection shall include measures to mitigate for flanking flows.

To ensure that stream bank repairs will not fail during high velocity flow events, armoring shall be keyed into the existing bank material.  Tying proposed improvements well into existing surfaces (buried armoring at the ends of the treatment areas) shall be done to limit potential for flanking damage.  This is particularly important at the beginning and end of proposed bank protection areas.  Filter blanket shall be installed immediately below the bank protection to prevent material from eroding around larger rock.  The filter blanket may be either geotextile fabric or a gradation of small rock and gravel and should consider the size of the primary armoring rock.  It is recommended that the design be consistent with USCOE methodologies.  The flexible types of bank protection proposed in the Bank Erosion Assessment, which tend to bend without breaking, should be used for bank protection.  This type of bank protection tends to settle and move rather than failing completely. 

Impact G-9.  Bank protection measures may cause changes in depositional or erosion patterns along the channel banks up- or downstream of the improvements.  This may result in protection for the improved area, but also result in adverse erosion to occur in adjacent areas.

Vegetation, rock armoring, and timbers are all bank protection components that influence the roughness (Manning’s N-value) of the channel banks.  Changes in roughness along a portion of the bank (i.e., from installation of bank protection) may cause increases or decreases in water velocity up- or downstream of the improvements.  Increases in water velocity may cause increased bank erosion in unprotected areas while decreases in velocity may increase sediment deposition.  Increased sediment deposition may result in decreased channel hydraulic capacity or changes in flow patterns in the channel that lead to increased erosion elsewhere.

Mitigation Measure G-9.  To prevent erosion problems upstream and downstream of bank repair sites, the design of bank protection shall consider effects to adjacent areas and design features to reduce impacts to up- and downstream adjacent areas.

To protect adjacent areas up- and downstream of bank repair sites, design of bank protection shall include transition protection for adjacent areas.  As necessary to attenuate potential velocity increases, the design shall incorporate energy dissipation features at the transition such as oversized rock, plantings, or check structures.

Hydraulic evaluation using the HEC-2 or HEC-RAS computer simulations (Mitigation Measure H-2) shall include an analysis of potential velocity changes in adjacent areas of the river.  If necessary, additional sections may need to be added to the model to define changes in nearby areas.  Field review of the overall condition of up- and downstream areas, including the existing level of bank protection in those areas, shall be conducted to support the hydraulic evaluation.

Impact G-10.  Deposition in the confluence area of the Salsipuedes Creek and Pajaro River may result in reduced capacity and increased frequency of overtopping of the levees.

The deposition of material at the Salsipuedes confluence zone (from the Southern Pacific Railroad bridge 3500 feet downstream of, to 500 feet upstream of, the Salsipuedes Creek confluence [Reach D, Figure 2.3-1 and Figure 2.3-2) is anticipated based upon sediment transport analysis and the history of past maintenance efforts.  The confluence area is also the area with the highest population density surrounding the river, and therefore is the area with the greatest risk of flood damage.

Mitigation Measure G-10.  To prevent potential flood hazards, the large sand bars in the confluence area shall be removed during the late summer in order to remove obstructions to flow prior to the wet season.

Only sandbars greater than 4 feet in height (above water level) and 250 feet in length and located in the Salsipuedes Creek confluence zone shall be removed.  Sandbar removal on the Pajaro outside of the Salsipuedes confluence zone is not part of this project.  If the County finds that sandbar removal outside of the Salsipuedes confluence zone is necessary because of threats to flooding and or the levee integrity, the County will obtain the necessary permits from regulatory agencies.

BIOLOGICAL RESOURCES
Impact W-2.  Removal of vegetation from the Pajaro River channel bottom between Murphy Crossing and Highway 1 would decrease the potential for formation of a concentrated low flow channel during the dry season and reduce shading of the channel.  High water temperature may have an adverse impact to out-migrating steelhead smolts during their passage from rearing areas to the ocean.

As water level declines in the Pajaro during the dry season, a low flow channel or series of braided channels forms across the relatively flat bottom of the Pajaro riverbed.  The location and configuration of the low flow channel(s) may change from year to year depending upon patterns of sediment deposition during the previous rainy season.  Under the proposed project, all in-channel vegetation, with the exception of a 5-foot-wide buffer on each side of the low flow channel, would be removed by hand and the stumps treated with herbicide during the summer of each year.  A 5-foot band of vegetation would be allowed to grow on either side of the low flow channel, although trees or shrubs would be cut at the base (manually) when stem diameters are greater than 3 inches.  In areas where braided channels form as water levels decline, County Public Works personnel would allow vegetation to develop only along the deepest channel.

Establishment of the 5-foot vegetation buffer is intended to improve habitat conditions for fish by causing water to concentrate along a defined pathway, facilitating the creation and maintenance of a low flow channel that is deep enough to allow steelhead passage.  In addition, the buffer would provide some shading of the channel that may lower water temperature during the dry season.  The buffer zone may reduce the impacts of in-channel vegetation clearance to a less than significant level for steelhead, but monitoring shall be conducted to evaluate the effectiveness of the vegetation management proposal.

Mitigation Measure W-2a.  To minimize loss of beneficial in-stream habitat characteristics for steelhead, annual monitoring of the effectiveness of the vegetative buffer along the low flow channel shall be conducted.

A comprehensive monitoring program shall be undertaken to evaluate the effectiveness of the vegetation buffer in facilitating the formation and maintenance of a low flow channel that meets the minimum depth requirements (if flow permits).  The monitoring shall be done by a qualified fisheries biologist and assess how quickly the vegetation buffer becomes established during the dry season, the effectiveness of the buffer in creating and maintaining a concentrated low flow channel, and under what flow conditions the buffer is ripped out during high velocity winter flows.

The Pajaro Valley Water Management Agency is required to maintain a minimum flow of 90 cfs, corresponding to maintaining 9 inches in riffle areas, for the area from Murphy’s Crossing to the Pajaro River mouth for one of their projects affecting the Pajaro River.  Therefore, this project has recognized this standard.  In the driest of years, however, there may not be any flow in late summer in some reaches of the Pajaro, despite a concentrated low flow channel.  A comprehensive monitoring program shall be undertaken to evaluate the effectiveness of the vegetation buffer in facilitating the formation and maintenance of a low flow channel that meets the minimum depth requirements (if flow permits).  The monitoring shall be done by a qualified fisheries biologist and assess how quickly the vegetation buffer becomes established during the dry season, the effectiveness of the buffer in creating and maintaining a concentrated low flow channel, and under what flow conditions the buffer is ripped out during high velocity winter flows.  Monitoring shall be conducted during the 20-year life of the project to allow for evaluation during both drought and flood cycles.  If monitoring concludes insufficient low flow channel depth, then the remedial actions specified by measure W-2c shall be implemented.

Mitigation Measure W-2b.  If the vegetation buffer is too sparse during some years to facilitate creation of a low flow channel, willow cuttings shall be planted along the low flow channel in the spring to enhance vegetation re-establishment.

To compensate for lack of sufficient low flow channel depth, spring willow planting shall occur along both sides of the thalweg segments where biological monitoring has determined is necessary to re-create adequate depth of the final thalweg.  Willow cuttings shall be obtained from existing vegetation in the immediate area and planted at 1.5-foot centers along both sides of the low flow channel.  Planting shall be conducted in early spring or late fall and be supervised by a qualified biologist.

Mitigation Measure W-2c.  Water temperatures shall be monitored to document temperature patterns along the Pajaro River and Salsipuedes Creek and evaluate conditions for migrating smolts.

Permanent stations shall be established along the Pajaro River and Salsipuedes Creek to evaluate water temperature during periods of smolt migration.  Continuous temperature monitoring devices shall be installed and set to record water temperature between April 1 and June 15 of each year.  Temperature shall be monitored along the Pajaro River at a minimum of 3 stations between Murphy Crossing and Salsipuedes Creek, 1 station at the mouth of Salsipuedes Creek, and 2 stations between Salsipuedes Creek and Thurwacker Bridge.  At least one station shall be established on Salsipuedes Creek below the Corralitos Creek confluence.  The locations of the stations shall overlap with permanent transects established to monitor vegetation and hydrologic conditions (Mitigation Measure S2a).  In addition, air temperature shall be monitored at each of the stations so that a correlation between air and water temperature can be determined.

If monitoring determines that temperatures rise above 24 degrees C for more than one hour during the day or the average temperature within any 24 hour period rises above 24 degrees C, the Public Works maintenance staff shall implement one or more of the following remediation activities listed below immediately:

·        Supplemental willow planting where buffer is sparse.

·        In channel earthwork to create low flow channel.

·        Increase width of vegetative buffer.

·        Allow buffer vegetation to grow taller.

Temperature monitoring shall continue to determine if the remediation actions are effective.  If they are not, additional remediation actions shall be implemented until monitoring concludes that temperature standards have not been exceeded.  The results of all monitoring shall be carefully recorded and documented as specified in the mitigation monitoring and reporting program for this project.

 “Mitigation Measure 6.4.3-2—Maintenance of Flow for Steelhead Migration: Vertical wells or infiltration gallery pumps will be operated only when flow in the Pajaro River is at least 90 cfs, which is expected to maintain a minimum depth in riffles of 0.75 ft.”

Impact W-3.  Establishment and maintenance of riparian vegetation from the toe of slope to near the top of bank on the Santa Cruz County side of the river would improve conditions for steelhead and several sensitive bird species and would be a beneficial impact of the project.

Conservation of riparian vegetation along the channel bank would shade the low flow channel and provide overhanging escape cover and channel scour where the low flow channel flows along the bank.  This would improve conditions for migrating steelhead and for resident warm water fishes.  This may also benefit several sensitive bird species including the Yellow Warbler and Yellow-breasted Chat that are dependent largely on dense riparian vegetation for nesting.

Mitigation Measure W-3.  The benefit of revegetation to birds shall be monitored with yearly surveys over the course of five years following restoration.

To adequately assess the success of restoration efforts and to compensate for the routine removal of vegetation with stem diameters greater than three inches, the restoration plantings on the stream bank shall be monitored by a qualified wildlife biologist annually for five years following the initial planting to determine how the habitat is being used by birds and other wildlife species.  This monitoring shall quantify the use of new habitat in terms of nesting, foraging and roosting within sample transects at representative locations along the river.  These surveys shall follow a standard protocol such as those established for Breeding Bird Surveys or Breeding Bird Atlases and be conducted by a qualified ornithologist at least three times per year.  Survey transects or blocks shall be established in at least five locations throughout the project area including three along the Pajaro River, one on Salsipuedes Creek and one on Corralitos Creek.  The monitoring shall make recommendations to correct any observed problems.  A monitoring report shall be prepared and submitted to County of Santa Cruz Public Works and Planning Departments on the same date each year.  This report shall recommend management activities and be available as guidance for similar projects.  Furthermore, Monterey County should be encouraged to establish riparian vegetation along the banks of the Monterey County side of the Pajaro.  The results of this monitoring will provide useful guidance towards such revegetation.

Impact W-4.  Periodic removal of accumulated sediment from the channel could adversely affect fish and other aquatic wildlife by destabilizing the low flow channel and increasing stream turbidity.  Other wildlife, such as western pond turtle, California red-legged frog and western snowy plover, may be impacted directly by heavy equipment and maintenance workers in the channel or indirectly by impacts to their food sources.

Removal of sandbars every 4 to 5 years at a single location could remove or alter the low flow channel and associated vegetation buffer and temporarily increase stream turbidity if activities were conducted when surface water is present.  Sandbar removal could cause significant adverse impacts to migrating steelhead if the low flow channel was removed or turbidity increased during migration periods.  Other wildlife of concern, such as western pond turtle and California red-legged frog, may be directly or indirectly impacted by sandbar removal activities.  These impacts are addressed in Impact W-9.

Mitigation Measure W-4a.  A meandering low flow channel shall be maintained during sand bar removal or reconstructed following in-channel work.

To prevent destabilization of the low flow channel, activities within the low flow channel shall be avoided during sand bar removal if possible.  If impacts to the low flow channel are unavoidable, a low flow channel shall be immediately reconstructed when sand bar removal is completed.  A five-foot band of willow cuttings shall be planted along both sides of the re-created channel to reestablish the vegetation buffer.

Mitigation Measure W-4b.  Measures shall be implemented to minimize turbidity during any in-water construction.

To minimize water turbidity during sandbar removal activities, temporary use of cofferdams or other measures to minimize turbidity shall be implemented if sand bar removal is conducted in areas with surface water.

Mitigation Measure W-4c.  Sandbar removal shall be conducted at the end of the summer (June 1 to October 15).

To further minimize water turbidity and prevent loss of special status fish species, sandbar removal shall be conducted at the end of summer (June 1 to October 15) when sedimentation effects would be short-lived and eliminated by winter rains.  No sand bar removal shall be conducted before July 1 to avoid potential impacts to out-migrating steelhead smolts.

Mitigation Measure W-4d.  Sandbar removal in the Pajaro River channel shall be limited to the Salsipuedes Creek Confluence Zone, which begins 3500 feet downstream of the confluence of Salsipuedes Creek and the Pajaro River at the Southern Pacific Railroad Bridge and extends 500 feet upstream of the Salsipuedes Creek confluence (Reach D, Figure 2.3-1 and Figure 2.3-2).  Only sandbars greater than 4 feet in height (above water level) and 250 feet in length and located in the Salsipuedes Creek Confluence Zone shall be removed. 

Sandbar removal on the Pajaro outside of the Salsipuedes Confluence Zone is not part of this project.  If the County finds that sandbar removal outside of the Salsipuedes Confluence Zone is necessary because of threats to flooding and/or the levee integrity, the County will obtain the necessary permits from regulatory agencies after subsequent environmental review is conducted.

Impact W-5.  Removal of fallen and leaning trees in Salsipuedes and Corralitos Creeks would decrease shade cover, escape cover and pool formation for resident and migrating steelhead.  This activity will also decrease estivation habitat for California red-legged frogs and basking sites for western pond turtle.

Project implementation would result in the removal of fallen and leaning trees that would block or divert storm waters in Salsipuedes and Corralitos Creeks.  In Corralitos Creek, from East Lake Avenue/State Highway 152 to the Browns Valley Bridge, these trees would be cut into 3- to 4-foot sections and left in place.  Their root structures would also be left in place.  This work would be conducted by hand during times of low flow and no equipment would be operated in the channel bottom.  These natural structures in the channel create pools and provide shading and escape cover for resident and migrating fish.  They also provide estivation habitat for California red-legged frogs and basking sites for western pond turtles.  Resident steelhead could be adversely impacted by the loss of habitat features from the Highway 129 crossing to the Pajaro River confluence.  Although suitable summer rearing habitat for steelhead is not present along the reach from Highway 129 to Highway 152, vegetation removal would reduce shade and escape cover for migrating steelhead.

In Corralitos Creek from Varni Road upstream, tree removal would have minimal effects on steelhead because this reach of the channel serves only as a seasonal migration pathway.  Between Highway 152 and Varni Road, steelhead rearing occurs in perennial portions of the stream in wetter years.

Loss of downed trees and in-channel woody vegetation in Salsipuedes and Corralitos Creeks could have a significant impact on the survival of steelhead smolts along reaches of the watershed where summer rearing occurs.

Mitigation Measure W-5a.  Large (3-foot) boulders or other structures anchored to the channel bed shall be placed in the channel at the toe of the bank to replace habitat lost by woody debris removal.

To compensate for the removal of fallen trees, entrained logs and other cover material used by steelhead and other aquatic species, maintenance crews shall incorporate large boulders or other structures into the toe of the slope as part of bank protection that should scour along the base of the rock to create pools and cover structure.  The placement of boulders in the channel would serve to create pools and escape cover for migrating and resident steelhead.

Mitigation Measure W-5b.  Fallen or leaning trees removed in all parts of Corralitos and Salsipuedes Creeks shall be cut into 3- to 4-foot sections and left in place.  Their root structures shall also be left in place.  These features will provide habitat for steelhead, western pond turtle and California red-legged frog.

As described above, leaving cut-up tree sections and root structures in the channel would provide shade and escape cover for fish and habitat for frogs and turtles.

Impact W-6.  Removal of vegetation on the levee slopes and benches along Salsipuedes Creek by mowing and herbicide application would impact a number of nesting birds.

Vegetation management on Salsipuedes Creek would occur with herbicide application three times each year on levee slopes (early spring, mid-summer and late summer) and twice each year on benches (mid summer and late summer).  Mowing would occur once each year in late June or early July.  Removal of this vegetation will impact birds nesting in these areas.

Mitigation Measure W-6.  No vegetation control work, including herbicide application, shall be conducted before July of that year to maximize the growth of vegetation for nesting birds and leave active nests undisturbed throughout the breeding season.

To minimize disruption of bird nesting and pre-fledging activities, maintenance crews shall conduct all mowing and spraying of vegetation on levee benches and slopes after July 1st each year.  If vegetation control work is conducted as described above, nesting birds in these areas may be heavily impacted.  If vegetation control measures are delayed until July each year, then birds will have the chance to complete the nesting cycle and will not be directly impacted by removal activities.

Impact W-7.  Bank stabilization and erosion control measures, using riprap or other bank protection measures, will reduce potential nesting habitat for the Bank Swallow and Northern Rough-winged Swallow.

The Pajaro River 1998 Bank Erosion Study (Northwest Hydraulic Consultants, 1998) identified 70 specific sites in need of erosion repair along the Pajaro River.  Following the 1998 flooding, USCOE repaired Priority 1 sites by installing rock riprap along the eroded slopes.  Currently, bank erosion protection has not progressed at any of the Priority 2 or 3 sites, but may in the future depending on conditions.  The intent of erosion control is to correct the tendency of the river channel to widen due to bank scour.  However, Bank Swallows require vertical banks with friable, sandy soils that form due to bank scour to dig their nesting holes.  Their decline in the state is largely due to loss of nesting habitat from bank protection and flood control projects.

Mitigation Measure W-7.  Implementation of bank stabilization measures shall be limited to areas that severely threaten the integrity of the levee system.

To minimize impact to Bank and Northern Rough-winged Swallow nesting habitat along the Pajaro River, some eroded banks shall be retained in a vertical (or nearly vertical) condition without bank repair where these eroded slopes pose no threat to the integrity of the levee system.

If swallows are present, appropriate mitigations should be developed in consultation with the appropriate trustee agencies.  Swallows may not be present for some time in the project area even though they historically occurred there because their nesting habitat (near vertical sandy banks) have been degraded by maintenance activities for so long.  Therefore, at least 5 areas with near vertical bank comprising an area of at least 25 feet in length and 5 feet in height will be retained on the Pajaro from Murphy’s Crossing to the river mouth to accommodate swallow nesting.

Impact W-8.  Use of herbicides Roundup and Rodeo to control the growth of vegetation along the levee benches and slopes could adversely impact wildlife.

Roundup and Rodeo are extensively used herbicides manufactured by Monsanto Company.  Glyphosate the active ingredient of Roundup and Rodeo is a wide-spectrum, non-selective herbicide that is effective against perennial grasses, broad-leaved weeds and shrubs.  Glyphosate-based herbicides are often selected because of their effectiveness in killing only the plants that are directly sprayed.  Rodeo and Roundup are similar except that (1) Rodeo contains a more concentrated form of glyphosate and (2) Roundup contains polyethoxylated tallowamine, a surfactant (an agent that attaches itself to suspended material) that can have toxic effects in water systems.  Because Rodeo contains no POEA, the Environmental Protection Agency’s Office of Pesticide Programs has approved its use over open water and wetlands.

The greatest potential for impacts to water quality from use of Rodeo or Roundup would be expected to occur from improper use of the products.  Use of Roundup in or directly adjacent to water could cause adverse affects to aquatic life, especially if it is discharged in higher than expected concentrations.  Either product could cause damage to native plant communities along the drainages if the herbicide is over-sprayed or the wrong plants are targeted.

Mitigation Measure W-8.  Rodeo and Roundup herbicides shall be applied in such a manner as to avoid over-spray or application of Roundup in or adjacent to surface water.  Herbicide application shall also be limited to areas where vegetation cannot be effectively mowed to control growth.

To protect wildlife using in-stream and riparian habitat from any toxic effects generated by the overuse of chemical herbicides, maintenance crews shall only use Rodeo and Roundup herbicides and they shall only be applied in the manner proposed by this project.  All maintenance crew personnel working with herbicides shall be certified in the use of chemical herbicides as required by state law.  Application methods proposed by the applicant would minimize the potential for adverse impacts from herbicide use to less than significant levels.  These methods include: 

·        Use of herbicide at or below concentrations recommended by the manufacturer

·        Use of proper precautions to avoid spills

·        Worker training to ensure that herbicide is sprayed only on target vegetation

·        Limited use of Roundup herbicide on levee slopes and benches (not slopes of the stream channel) in Salsipuedes Creek during the dry season (July 1 to October 15)

·        No use of herbicides anywhere in the channel bottom

 

Furthermore, where vegetation can be effectively mowed, such as on levee benches where mowers have easy access and the area is relatively flat, mowing shall replace herbicide application to control vegetation.

 

Impact W-9.  Vegetation removal, sandbar removal and other work in ponded areas of Corralitos and Salsipuedes Creeks will impact the California red-legged frog.

Adult California red-legged frogs require dense, shrubby or emergent riparian vegetation closely associated with deep, still or slow-moving water.  Therefore, the few ponded areas that exist within the project area provide critical refuge for frogs.  Any activities in these ponded areas may have a significant impact to frogs, if they are present, and these impacts shall be avoided.

 

Mitigation Measure W-9a.  Vegetation removal, sandbar removal and other work shall be avoided within ponded areas of Corralitos and Salsipuedes Creeks to avoid impact to California red-legged frogs.

Activities in ponded areas may directly impact frogs that are present or indirectly impact frogs through impacts to suitable habitat.  Therefore, activities shall be avoided in ponded areas.

 

Mitigation Measure W-9b.  Maintenance workers shall be briefed on the potential presence of California red-legged frog and western pond turtle in work areas and be informed of avoidance measures to be employed.

Measures to avoid “take” of California red-legged frogs include not removing fallen logs and branches that provide upland frog habitat, not filling in small rodent burrows or other potential frog refuges and limiting herbicide application to dry, upland areas.

 

Mitigation Measure W-9c: Conduct surveys for suitable Red-legged frog habitat 24 hours prior to vegetative clearing or levee work and avoid identified suitable habitat areas.

In addition to implementing mitigation W-9b, avoiding take of California red-legged frogs and their habitat can be accomplished by identifying and avoiding suitable habitat for the species.  Twenty-four hours prior to conducting levee work or clearing of vegetation in the stream channel or banks, surveys shall be conducted by trained personnel to identify suitable habitat.  Public Works maintenance crews could be trained to conduct these surveys by a qualified biologist.  The location of identified habitats shall be communicated to other maintenance crewmembers and clearing or excavation work (eg. sand bar removal) shall be avoided where these habitats occur.

Mitigation Measure W-9d: Annual monitoring will be conducted to determine if backwaters form because of the established 5-foot vegetation buffer for the low channel.  If backwaters do not form, initiate a bullfrog eradication program on Hansen and Harkins Sloughs to benefit area-wide populations of the red-legged frog.

The Biological Assessment report prepared for BioSearch for this EIR discussed the lack of backwaters (with low or non-existent stream flows) in the Pajaro River channel as a major characteristic that is detrimental for the survival of red-legged frogs.  The EIR preparers anticipate the new backwaters will form as a result of establishing a permanent vegetative buffer for the river’s low flow channel.  The USFWS has requested that the formation of these new backwaters be documented through annual surveys by a qualified biologist.  The creation of backwaters will enhance the in-stream habitat for the species.  If backwaters do not form in substantial numbers, then other measures will be conducted to benefit area-wide populations of the frog.  The off-site measure recommended by USFWS is that Public Works maintenance crew conducts a bullfrog eradication program in Hansen Slough and Harkins Slough to remove this primary predator of red-legged frog larvae.  The Mitigation, Monitoring, and Reporting Program will provide details on how this eradication program would be conducted.

Impact W-10.  Rodent control along the Pajaro River and Salsipuedes Creek may directly or indirectly affect the California red-legged frog.

Fumitoxin, a Category 1 pesticide, is used by placing moisture-activated pellets in rodent burrows and then closing the burrow entrance.  During the dry season, California red-legged frogs take shelter in landscape features that provide cover and moisture including small mammal burrows.  Rodent control activities may directly impact frogs taking shelter within targeted burrows or indirectly impact frogs by eliminating potential shelter areas.

 

Mitigation Measure W-10.  Rodent control using pesticides shall not be conducted along Salsipuedes Creek to avoid impact to California red-legged frogs.  Rodent control using pesticides along the Pajaro shall be limited to areas where rodent burrows severely threaten the integrity of the levee wall.  Rodent control activity shall also be limited to no more than 12 feet from the base of the levee and not be conducted along the outer benches or banks.

Rodent control may directly impact California red-legged frogs and may also indirectly impact raptors such as Red-tailed Hawk (Buteo jamaicensis) and American Kestrel (Falco sparverius), which hunt rodents on the river’s banks and benches.

 

Impact W-11.  The Western Snowy Plover breeds on the sandbar at the Pajaro River mouth and sandbar modification during their breeding season (late spring and summer) would negatively impact this federally threatened species.

The Santa Cruz County Department of Public Works has permits to open (and attempt to re-close) the sandbar at the mouth of the Pajaro in late spring or summer if high lagoon water levels produce flooding.  The breeding season of the coastal population of the western snowy plover extends from mid March through mid September.  Nest initiation and egg laying occurs from mid March through mid July (USFWS, 1993).  Mechanical sandbar breeching is considered a potentially significant impact to this threatened species.

 

Mitigation Measure W-11.  Impact to breeding Western Snowy Plovers, if present, shall be avoided during modification of the sandbar at the mouth of the Pajaro River.

A qualified wildlife biologist shall inspect the sandbar area slated for removal prior to any removal activities to determine if snowy plovers will be impacted.

 

Impact W-12.  Maintenance equipment used within or near a wetted channel may leak grease, oil and/or fuel into the channel and this would negatively impact aquatic wildlife.

Oil, grease and fuel are toxic to wildlife and their entry into the Pajaro River system from the use of maintenance equipment shall be avoided.  Oil, grease and fuel entering the Pajaro River system will have a negative on steelhead, California red-legged frog, tidewater goby and other aquatic wildlife.

 
Mitigation Measure W-12.  Any maintenance equipment that within or near a wetted channel will be inspected to be free of grease, oil and fuel that could enter the watercourse.  Heavy equipment will only cross a wetted channel in very extreme cases.  In all circumstances, when operating heavy equipment within or adjacent to the wetted channel, fuel and oil tanks/pans should be surrounded by secondary containment devices.  Hydraulic oils will meet, at minimum, Environmental Protection Agency aquatic toxicity requirements and be biodegradable.

Maintenance equipment includes heavy equipment such as front loaders, excavators, dump trucks as well as smaller equipment such as chainsaws.

Impact W-13.  Maintenance activities below Highway 1 impacts listed species in the Pajaro.

The NMFS and CDFG commented that maintenance activity below Highway 1 does not significantly improve the flood carrying capacity of the river, yet significantly impacts listed species in the Pajaro.  Impact W-1 (p. 103) states “vegetation in the channel bed [below Highway 1] is presently very scarce because of brackish water inundation by tides and sandbar development” and that “downed trees in the wide sandy channel downstream of Highway 1 are generally scarce, even without maintenance”.  Furthermore, the Pajaro River Management and Restoration Plan (CH2M Hill 1997, p. 26) states “vegetation removal below Highway 1 does not significantly affect river capacity upstream of the Highway”.

 
Mitigation Measure W-13.  In-stream vegetation (except invasive weeds) or woody debris in the channel bottom below Highway 1 will not be removed.

The County has re-evaluated maintenance activities below Highway 1 and concluded that a reduction in vegetation maintenance is appropriate.  There is an intrinsic benefit of in-stream vegetation and woody debris to listed species in the Pajaro, and removal of this material may have a significantly impact.  Therefore, the County will no longer remove vegetation (except for invasive weeds) and woody debris in the channel bottom below Highway 1.

AIR QUALITY

Impact AQ-1.  Levee maintenance, bank erosion repair, vegetation maintenance and revegetation activities would generate PM10 (dust) emissions.

Under the proposed project, levee maintenance activities along the Pajaro River and Salsipuedes Creek would generate dust emissions from grading and equipment transport along dirt roads.  Similarly, bank repairs and revegetation along the Pajaro River and vegetation maintenance along the Pajaro River, Salsipuedes Creek, and Corralitos Creek would generate dust emissions from equipment and vehicles traveling to the site along dirt roads.  In addition, river maintenance would include removing silt from streambeds and flap-gates along the Pajaro River and Salsipuedes Creek.  The following discussion addresses dust emissions associated with silt removal, travel on dirt roads, and grading activities.

Dust Emissions from Silt Removal

According to Santa Cruz County (Reynolds, Personal Communication, 1999), up to 150 cubic yards of silt per day would be removed from the Pajaro River during sand bar removal, 40 cubic yards of silt per day would be removed from Pajaro River flap-gates, and 6 cubic yards per day would be removed from Salsipuedes Creek.  Removed silt generally has high water content and would not be dried before transport to the County of Santa Cruz Public Works maintenance yard.  Table 3.5-3 provides an estimate of the amount of dust that would be generated by silt removal activities.

Dust Emissions from Travel on Levee Roads

Equipment and vehicles driving on dirt roadways to access the project site would generate dust.  To access the Pajaro River and Salsipuedes Creek, the equipment and vehicles would travel along approximately ¼ mile of dirt farm roads.  The remainder of road travel would be on paved roads or roadways surfaced with base rock and screenings.  Calculations of dust emissions were conducted using a total travel distance of 0.5 mile per vehicle to account for the return trip and additional travel necessary to access different areas of the river.  Dust emissions that would be generated from travel by equipment and vehicles for each activity are presented in Table 3.5-3.

Dust Emissions from Grading

Grading during levee road maintenance or implementation of bank stabilization measures would generate fugitive dust when equipment wheels or blades pulverize and brake down surface material.  Wind erosion or vehicle tires; subsequently entrain the dust generated, including PM10.  The MBUAPCD assumes that grading and excavation activities generate approximately 71 pounds of PM10 per acre (MBUAPCD, 1995).  According to the County (Reynolds,Personal Communication,1999), up to one acre would be graded on any given day.  Based on this level of activity, grading associated with levee and access road maintenance or bank repair would generate approximately 71 pounds of PM10 per day.

Summary of Dust Emissions

Dust emission levels that would be generated by each project activity are shown in Table 3.5-3.  As the results indicate, no single activity would be expected to emit PM10 above the MBUAPCD significance threshold of 82 pounds per day.  However, two or more activities combined could exceed the PM10 threshold.

Mitigation Measure AQ-1.  Limit grading and similar activities to those that will generate less than 82 lbs/day of particulate matter (dust).  To minimize dust generation and its effects on nearby residential and agricultural uses, the Public Works Department shall schedule grading and related maintenance activities so that a single area of less than one acre is being disturbed within a single workday.  If this is not possible, then the grading site shall be watered with a spray truck constantly during the workday. 

Two or more maintenance activities that, when combined, would generate PM10 emissions exceeding the MBUAPCD threshold (82 lbs/day), shall not be conducted on the same day.  Grading operations (bank erosion repair and levee and access road maintenance) are in terms of lbs/day/acre.  Therefore, dust generation can be reduced below tabulated values by working on areas less then 1 acre in size.  Should a combination of activities be contemplated which would exceed MBUAPCD thresholds, then watering 2-3 times per day for earthmoving and excavating activities will need to be employed to reduce this contribution from 38 lbs/day/acre to 29 lbs/day/acre.

NOISE
Impact N-1.  Earthmoving equipment, service vehicles, mowers, chain saws, wood chippers and other equipment used for proposed maintenance would generate noise.

Noise would be generated by levee and access road maintenance along the Pajaro River and Salsipuedes Creek from trucks and equipment traveling to the site to repair potholes and shoulder along levee roads.  Noise associated with grading and other road repair activities would be audible by residences located adjacent to the levees in the short reach of the river through the Town of Watsonville.  Bank erosion repairs along the Pajaro River would generate noise from service vehicles used to approach the site and the use of equipment such as excavators, loaders and dozers.  Vegetation maintenance activities would generate noise along the Pajaro River, Salsipuedes Creek and Corralitos Creek from the use of service vehicles, chain saws, wood chippers and mowers.  These vegetation management activities and the noise produced by them will be similar to those currently going on under the interim Coastal Zone/Riparian Exception permit, as identified in the setting section.

The nearest sensitive receptors to the project site are homes in the City of Watsonville along the Pajaro River and Salsipuedes Creek.  The nearest residence to proposed work areas is adjacent to the Pajaro River levee just downstream of the Salsipuedes Creek confluence.  The residence is approximately 50 feet north of the levee and 200 feet north of the toe of the channel bank.  Residences within 50-100 feet of the levees may experience fairly high noise levels, but the noise would be short-term (3-5 days annually) and limited to the hours between 8 AM and 5 PM.  The levee will act to attenuate noise generated as a result of work on the banks, benches and channel areas.  Residences greater then 100 feet should not be significantly impacted.  Because of the extremely limited number of homes that lie within 100 feet, the attenuation effects of the levees, and the extremely limited duration of project work in the area of the homes, noise impacts are expected to be less then significant.

Mitigation Measure N-1.  All equipment shall be outfitted with mufflers and their operation limited to the hours of 8a.m. to 5p.m. weekdays.
To minimize noise generated by maintenance activities and its effects on nearby residential areas, the Public Works Department shall ensure that all maintenance activities comply with the following:

·        Equipment operation onsite shall be limited to the hours of 8 a.m. to 5 p.m. weekdays (except in emergency situations).

·        All equipment shall be equipped with mufflers that are in good working condition.

 

LESS THAN SIGNIFICANT IMPACTS

In addition to the impacts the mitigations listed above, the EIR identified several impacts of the project which are less than significant and therefore no mitigation measures are required.  Findings are not required for less than significant impacts.  However, these less than significant impacts are listed at the end of these findings to clearly identify which impacts identified in the EIR result in insignificant effects and to note which impacts do not require mitigation measures.  The listing of these insignificant impacts is also included to provide an explanation why these impacts have been determined to be insignificant.

 

Impact H-1.  Establishment of vegetation in the channel bottom and along the channel banks of the Pajaro River will reduce the conveyance capacity of the channel and therefore increase the flood risk compared to existing conditions.

No significant impact.  The full implementation of the proposed vegetation management plan results in a less then 1% decrease in channel capacity in relation to current (July 2000) and baseline (February 1999) conditions.  The proposed plan includes provisions for monitoring to ensure that vegetation growth stays within plan guidelines.

Mitigation Measure H-1: No mitigation is necessary.

Impact G-1.  Levee resurfacing and maintenance could cause levees to erode or fail as a result of increasing the height of the levee slope, placement of additional load on the levee, or inadequate soil compaction.

The proposed project would involve (1) resurfacing the Pajaro River levee in Monterey County to restore the levee to its original elevation and (2) ongoing resurfacing as needed to maintain the Pajaro River (Monterey and Santa Cruz Counties) and Salsipuedes Creek levees at their original 1949 elevations and to provide a consistent level of protection.  This activity would increase the height of the slope and load on the slope.  As a result of substantial increases in levee height, levees could become susceptible to static instability, a condition in which the levees could collapse under their own weight.  Poorly compacted soil could erode from wind or flooding activity.  Increased slope and height could cause added material to topple if it is not placed and compacted adequately.  Failure of the additional material could also occur as a result of liquefaction during an earthquake.  Slope failure or erosion could result in infilling of the river channel and reduction of the hydraulic capacity of the river or levee failure and possible over bank flow during flood events.  This would be a significant impact.  Levee resurfacing is not anticipated to result in an elevation increase of more then 1-2 feet.  An assessment of this degree of resurfacing indicates that the quantity of material proposed to be added and the anticipated change in height would not be enough to cause any of the above indicated consequences.  Consequently, any stability or erosion impacts related to the levee resurfacing and maintenance are expected to be less then significant.

Mitigation Measure G-1.  No mitigation is necessary.

Impact G-3.  The proposed bank erosion restoration along the Pajaro River would reduce the likelihood of bank/slope erosion, slumping and levee failure caused by exposing bank soil to wind and scour from flooding.

The proposed project has identified 37 areas of significant erosion threat (half of which have been armored on an emergency-basis by the USCOE).  As described under Mitigation H-2, erosion restoration will be provided to reduce bank erosion and the threat of levee failure.  Eight alternative treatments are proposed that combine rock protection, regrading of channel banks and biotechnical (i.e., use of vegetation) stabilization methods.  None of the methods suggested increases the threat of instability from seismic events for the treated and adjacent areas.  More basic techniques of laying back (reducing the slope angle) bench slopes to allow for greater vegetation success will only increase stability for seismic events.  All suggested bank stabilization techniques are expected to have positive, but varying degrees, of effectiveness.  As defined under Mitigation H-2, site-specific characteristics will need to be evaluated at the time of the repair design and consideration given to potential for impacts to adjacent areas and the opposing bank.

Mitigation Measure G-3a:  Long-term effects.  No mitigation is necessary.  In the long-term, this is a beneficial impact.

Impact G-6.  Revegetation of the banks of the Pajaro River would reduce bank erosion caused by soil exposure to wind and scour from flood and would thus improve bank stability.

Under the proposed project native riparian vegetation would be established along the channel bank from the toe of slope up to 8 feet below the top of bank on the Pajaro River from Highway 1 to Murphy Crossing.  In addition, vegetation would be left to grow naturally on the toe of slope, along the lower channel slope and channel bench on Salsipuedes Creek from the confluence with the Pajaro River to State Highway 129 and on the east side of Salsipuedes Creek from Lakeview Road to East Lake Avenue/State Highway 152.  Vegetation planting and regeneration will reduce bank erosion by providing soil cover and root stabilization.  This will decrease the potential for bank slope failure and subsequent levee instability.  This would be a beneficial impact.

Mitigation Measure G-6.  No mitigation is necessary.

Impact G-7.  Vegetation management on channel banks along reaches of the Pajaro River and Salsipuedes Creek may potentially cause bank erosion.

Under the proposed project, vegetation management along the Pajaro River from Highway 1 to Murphy Crossing would include removing dense vegetation on the upper channel banks.  The removal of vegetation from the upper channel banks will include only the hand removal of woody vegetation with a stem diameter of three (3) inches or greater.  If water reaches the upper channel bank where the clearance of the larger woody vegetation has occurred, there is a potential that this area may be subject to erosion.  However, because the lower channel bank will be vegetated and the upper channel bank will have ruderal annual grass vegetation and smaller woody vegetation there is little likelihood that such erosion will cause bank/slope or levee instability.  Because this vegetated condition is relatively consistent with the baseline 1999 condition, this impact is considered less then significant.

Mitigation Measure G-7.  No mitigation is necessary.

Impact W-1.  Clearance of downed trees on the Pajaro River downstream of Highway 1 would remove potential escape cover and limit deepwater habitat for steelhead and tidewater goby.

Maintenance actions will remove downed trees and woody vegetation greater than 3 inches in diameter from the channel bed.  However, vegetation in the channel bed is presently very scarce because of brackish water inundation by tides and summer sandbar development.  Although they provide some escape cover for fish, downed trees in the wide sandy channel downstream of Highway 1 are generally scarce, even without maintenance and do not provide backwater or significantly deeper habitats.  Consequently, this potential impact is not considered significant.

Mitigation Measure W-1.  No mitigation is necessary.
 
Impact AQ –2.  Levee maintenance, bank erosion repair and vegetation maintenance would result in vehicle exhaust emissions from the use of excavators, tractors, loaders, dozers, dump trucks, pickup trucks, utility trucks and emissions from chain saws and wood chippers

Calculating ROG and Nox emissions from construction activities is not necessary because these temporary emissions of these ozone precursors have been accommodated in State- and Federally –required air plans.

Mitigation Measure AQ-2.  No mitigation is necessary

Impact V-1.  Vegetation management along the Pajaro River and Salsipuedes Creek may impact the scenic quality of views from scenic routes.

Under the proposed project, vegetation management activities along the portions of the Pajaro River that would be visible from Highway 1 would include: (1) removal of invasive weeds and woody vegetation growing in the channel; (2) mowing or herbicide application on upper channel banks, channel benches, and levee slopes; and (3) establishment of riparian vegetation along the lower channel banks.  Vegetation management activities along Salsipuedes Creek that would be visible from Highway 152 would include (1) mowing and herbicide application on channel benches and levee slopes; (2) removal of woody vegetation from the channel bottom and banks, and (2) natural growth of vegetation along the east side of the channel.  Despite these activities, the impact from vegetation management on views from Highway 1 and Highway 152 is expected to be minimal and less than significant for the following reasons:

·        Minimal vegetation would be removed from the Pajaro River stream channel or banks on the coastal side (west side) of Highway 1 (Coastal Zone area);

·        Most vegetation removal would occur in the river channel which is located at a lower elevation than the roadways and obscured by levees which are above adjacent grade and therefore is not easily viewed by motorists traveling along Highway 1 or Highway 152;

Ÿ         Highway 1 and Highway 152 intersect at a minor area of the entire project area and thus, most of the stream clearance activities will not be visible from these two roadways.

Proposed vegetation management would improve views (in relation to February 1999 conditions) of the Pajaro River upstream of Highway 1 by planting riparian trees and shrubs along portions of the channel banks (and/or allowing natural establishment) that are currently lacking riparian vegetation.  In addition, riparian trees would be established along the channel benches to create a savanna-type landscape.  Areas treated with rip rap during emergency USCOE flood repairs will be slower to revegetate, but are expected to gradually increase in vegetation coverage over time.

Mitigation Measure V-1.  No mitigation is necessary.

 

Impact V-2.  Vegetation management and bank erosion restoration would alter the scenic quality of the Pajaro River and Salsipuedes Creek as viewed from the levees.

As described in impact V-1, vegetation management along the Pajaro River and Salsipuedes Creek will involve both vegetation removal and planting and natural regeneration and growth.  The visual quality of the view from the levees along these streams is expected to improve from the removal of ruderal vegetation and the planting and natural growth of native riparian vegetation.  Therefore, the impact from vegetation management on the scenic quality along the levees would be beneficial.

The bank erosion restoration along the Pajaro River would involve a combination of traditional structural armoring methods and bioengineering techniques (i.e., planting).  The artificial nature of some of the traditional treatments would have an impact on the visual quality of the Pajaro River bank as viewed from the levee.  However, the erosion sites are sporadic along the riverbank, and the impact would be temporary as natural vegetation grows in.  As a result, the impact from bank erosion restoration on the scenic quality along the levees would be less than significant.